Water Supply Improvement Scheme

PUBLIC HEALTH AND MUNICIPAL ENGINEERING DEPARTMENT
BRIEF NOTE ON  KHAMMAM  WATER  SUPPLY  IMPROVEMENT  SCHEME UNDER 
UIDSSMT (SUB PLAN OF JNNURM)
1 Administrative Sanction G.O.Rt.No.1178 , Dt.17-09-2011,  for Rs.7410 Lakhs
2 Technical Sanction ENC(PH)  R.No:76/2011-12 ,Dt:23-11-2011,                                                           for Rs.5070.90 Lakhs Civil Works & 2330.10 Lakhs for O&M for 7 years (including 2 Yers Defect liability period)
3 Foundation Stone Laid By Hon’ble Chief Minister on 24-11-2011.
4 Tender Approval G.O.Rt.No: 97 , Dt: 23-01-2012
5 Name of the Agency Sri. Velagapudi Rama Rao
6 Agreement  No SE CR (PH) Wgl No.12/2011-12, Dt:02-02-2012.
7 Agreed period of Completion 24 Months.
MAIN COMPONENTS OF SCHEME STAGE OF WORK
1 Raising & Strengthening of Weir across Munneru River The CE CDO recommended for construction of new weir instead of raising the height of existing weir.Hence the revised estimate has forwarded to ENC(PH) ,Hyderabad.
2 8.0 m dia Intake Well cum Pump House Pump House Roof Slab Completed(95%)
3 16.5 MLD Rapid Gravity Filtration Plant at Danavaigudem Head Works Roof Slab completed(80%)
4 700 KL Clear Water Sump at Danavaigudem Head Works PCC for Foundation Completed(35%)
5 Clear Water Pump House at Danavaigudem Head Works Yet to be started (dependent work of Sump)
6 1200 KL capacity ELBR at Ramanagutta Completed up to 1st Brace level(35%)
7 600 KL capacity ELBR at Raganayakulagutta Bottom Dome completed& side wall is in progress(88%)
8 600 KL Capacity ELSR at NSP Camp  up to 4th Brace completed(50%)
9 500 KL Capacity  ELSR at Khilla  up to 4th Brace completed(50%)
10 500 KL Capacity  ELSR at Pakabanda Bazar  up to 4th Brace completed(50%)
11 1000 KL Capacity  ELSR at Parikamukkala Colony 1st Brace Completed (40%)
12 1200 KL capacity ELSR at Teachers Colony Top Dome completed(95%)
13 250 KL Clear Water Sump at Ranganayakula Gutta Yet to be started
14 Raw Water & Clear Water Pumpsets Pumpsets Supplied
15 Pumping Mains & Gravity Mains 6.20 km laid against 12.34 kms.
17 Distribution Lines 43.50 km laid against 57.67 Kms
18 Staff Quartes & Compound Walls Yet to be started
TOTAL AMOUNT OF WORK DONE  (up to 07-11-2013)  is       27.96 Crores(65 %)        against 43.07 Crores

}